The Sequoia Office Building in Nové Roztyly Enters the Next Phase of Construction
30. 06.
2026
PRESS RELEASE Prague, June 10 2026
The Sequoia office building, currently under development as part of the revitalization of the Nové Roztyly locality in Prague 11, has reached another major milestone. Following the completion of the excavation pit, the foundation slab has also been successfully finished. This definitively outlines the footprint of the building’s substructure, allowing construction to proceed with the underground and subsequently above-ground floors. The project is technically demanding due to both its scale and its location on sloping terrain with an elevation difference of up to 13 meters, as well as being situated below the groundwater level. The project is being developed by Passerinvest Group and GEMO, which also serves as the general contractor, and is scheduled for completion in the first half of 2028.